What usually goes wrong when buying an under-construction flat in Bengaluru?

In Short: The common problems are late possession, changes to the plan, a smaller carpet area or higher final bill than expected, a missing occupancy certificate at handover and weak handover of common areas. Most of them show up early on the RERA page, the site and the demand letters, and the RERA Act gives you specific rights on each, if the agreement and your records are in order.

Verify with your lawyer before acting. This page explains public rules and common checks, not a legal opinion on a specific property. Have your own property lawyer read the documents before you sign or pay.

When buyers tell us their under-construction purchase went wrong, the story usually has the same shape. Something small showed up early, nobody acted on it, and by the time it was obvious the options had narrowed. I have set out the usual problems as a table with the early sign and what to do, so you can watch for them from booking to handover.

The usual problems, their early signs and the rule that helps

Common under-construction problems
ProblemEarly signWhat helps
Late possession Quarterly RERA updates show slow progress; site activity drops s.18: interest for each month of delay, or refund with interest if you withdraw
Plan or layout change New towers or amenities appear in marketing s.14(2): changes to plans need two-thirds of allottees' written consent
Smaller carpet area Measurements on possession differ from the agreement Carpet area as defined in s.2(k) and the agreement terms
Higher final bill Demand letters add new heads The agreed cost sheet and escalation clause
No OC at handover Possession offered "pending OC" s.11(4)(b): promoter must obtain the OC
Defects after moving in Seepage, cracks, lift or pump failures s.14(3): five years to report structural and workmanship defects

How do you watch progress?

  • Read the RERA quarterly update each quarter. See how to read a QPR.
  • Visit the site every few months and note the floors cast.
  • Compare each demand letter with the stage it claims, before you pay. With a construction-linked plan, the stage should be visible.
  • Keep a single file of the agreement, payments, receipts and emails.

What if the project slows down?

Write to the builder asking for the revised schedule and the reason. Check whether the registration has been extended under s.6, which allows a total of one year for force majeure or reasonable cause. Our page on RERA extensions explains what that changes and what it does not. If EMIs are running, see who pays EMI during a delay.

What if the builder is in financial trouble?

Signs include unpaid contractors, stopped work across several projects and an insolvency petition. Homebuyers have specific rights in insolvency proceedings. See builder insolvency and homebuyer rights. Talk to a lawyer early, and coordinate with other buyers through the association or a buyer group.

How do you reduce these risks at booking?

  1. Prefer a construction-linked plan over a time-linked one.
  2. Check the builder's past projects and delays, which must be disclosed at RERA registration (s.4(2)(b)).
  3. Read delay, cancellation and escalation clauses before the token.
  4. Pay only through the project's bank account details on the RERA page, so the 70% escrow rule in s.4(2)(l)(D) works for you.
  5. Plan your finances for a delay, so a late handover does not force a distressed decision.

Frequently asked questions

Late possession. Watch the RERA quarterly updates and the site from the start, so you notice slow progress early.

Under s.18 of the RERA Act you can claim interest for each month of delay, or withdraw and claim a refund with interest. Karnataka's rules set the rate at SBI's highest MCLR plus 2%.

Changes to sanctioned plans or common areas need the written consent of at least two-thirds of allottees under s.14(2), apart from minor alterations.

Measure it against the carpet area in the agreement, using the RERA definition. See our page on carpet area mismatches for the next steps.

It is risky. The promoter is responsible for getting the OC. Ask for it, and take legal advice before you accept possession without one.

Five years from possession for structural and workmanship defects under s.14(3). The promoter must fix them within 30 days, without charge.

Compare quarterly RERA updates over time, visit the site, and check whether demand letters match visible progress.

Not automatically. The extension is about registration. Your rights under the agreement and s.18 need separate legal advice.

Generally yes, because payments follow visible stages. A time-linked plan asks for money on dates, whatever the progress.

The agreement, every demand letter, payment receipts, the RERA page printouts by quarter and all emails with the builder.

References

  1. Real Estate (Regulation and Development) Act, 2016, full text (Karnataka RERA copy): https://rera.karnataka.gov.in/resources/staticpage/Real_Estate_Act.pdf, accessed 17 Nov 2026
  2. Karnataka Real Estate (Regulation and Development) Rules, 2017 (NAREDCO copy): https://naredco.in/notification/pdfs/Karnataka%20Real%20Estate%20(Regulation%20and%20Development)%20Rules,%202017.pdf, accessed 17 Nov 2026
  3. Karnataka RERA portal: https://rera.karnataka.gov.in/, accessed 17 Nov 2026

This page explains public rules and processes. It isn't legal or tax advice. acre&key gives buyers advice for free.